#项目管理每日一题#
一位新项目经理在项目规划阶段加入项目。在审核项目文件后,项目经理发现项目管理计划是最后一份创建的文件。 项目经理应该查阅哪一份文件来分配资源以实施该计划?
A new project manager joins a project during its planning phase. Upon reviewing the project documents, the project manager discovers that the project management plan was the last document create What should the project manager reference to assign resources to implement the plan?
A:资源日历 Resource calendars
B:范围管理计划 Scope management plan
C:项目组织图 Project organization chart
D:资源管理计划 Resource management plan
正确答案:D
解析:PMBOK(6)P318,9.1.3.1-资源管理计划。
资源管理计划提供了关于如何分类、分配、管理和释放项目资源的指南。既然已经提到了"分配资源”,所以要选择资源管理计划。
选项A,资源日历是资源可用的时间表。
选项C,项目组织图通常用于阐明汇报层级关系。